Ted and I signed contracts for four major home projects in 2020 and learned immediately–with our first contract–that nothing was going to be finished quickly.
Hot tub: 22 weeks. Signed contract June 13; installed November 13.

Replace fascia and paint shutters: 16 weeks. Signed contract August 26; finished December 14.

Update home media: 10 weeks. Signed contract November 4; installation complete January 14.

Replace kitchen bay window and basement windows: 22 weeks. Signed contract August 31; installation complete February 2.

Our 2020 house projects are finally finished. When we started, we had no idea it would take so long; by the time we finished, we’d come to accept long delays as the 2020 way things are done.